On April 30, 2024, during his working visit to the Khmelnytsky NPP, head of JSC “NNEGC “Energoatom” Petro Kotin held a staff meeting on the completion of Units 3 and 4.
During the meeting, the reports of the responsible executors were heard and a number of issues were considered, in particular:
“Currently, activities on the arrangement of the reactor compartment are being completed, and active works are underway in the control room. In fact, we are working according to our schedule, and we will be ready for the installation of equipment on Unit 3 already in June of this year,” Petro Kotin emphasized.
Besides, the first modular houses provided by the Swedish government have already arrived for specialists who are involved in restoration works at the KhNPP units. These fully furnished and comfortable houses will be installed in a specially designated area in the nearest future.